The timeline slide outlines key project phases from Weeks 1-10 in January to March 2025, starting with a holiday break in Week 1, followed by knowledge transfer preparation in Weeks 2-3, and shadowing current processes in Weeks 4-6. It culminates in the go-live milestone in Week 9 and the initiation of hyper care support in Week 10 to ensure post-launch stability.
Timeline: Weeks 1-10 (Jan-Mar 2025)
Week 1, Jan 2025: Initial Holiday Break Project team takes holiday before commencing activities in the new year. Weeks 2-3, Jan 2025: Knowledge Transfer Preparation Prepare materials and schedule sessions for effective knowledge handover. Weeks 4-6, Feb 2025: Shadowing Current Processes Team shadows existing operations to understand workflows and responsibilities. Week 9, Mar 2025: Go-Live Milestone Achieved Official project launch with all preparations completed successfully. Week 10, Mar 2025: Hyper Care Support Starts Intensive monitoring and support provided post go-live to ensure stability.