The slide summarizes a project schedule in a table, listing tasks from Design to Finishes with start dates, durations in weeks, end dates, and statuses. Design is completed (Jan 2024), Foundation is in progress (ending Mar 2024), and Structure, MEP, and Finishes are planned through October 2024.
Project Schedule Summary
{ "headers": [ "Task", "Start Date", "Duration (weeks)", "End Date", "Status" ], "rows": [ [ "Design", "2024-01-01", "4", "2024-01-29", "Completed" ], [ "Foundation", "2024-02-01", "8", "2024-03-28", "In Progress" ], [ "Structure", "2024-04-01", "12", "2024-06-25", "Planned" ], [ "MEP", "2024-07-01", "10", "2024-09-02", "Planned" ], [ "Finishes", "2024-09-03", "8", "2024-10-28", "Planned" ] ] }